Let’s find what you’re looking for...
The August 2026 Operational Performance Factsheet breaks down how Nigeria’s grid-connected power plants performed during the month. Highlights: Average Available Capacity: An average of 4,758 MW was available for dispatch during the month. Average Load Factor: 86%, showing that 4,102 MW of the available generation capacity was utilised on average. Top Energy Producers: Afam_2, Kainji_1, […]
Our latest Metering Factsheet is here! The May & June 2026 Metering Status of Distribution Companies (DisCos) factsheet highlights continued progress in customer metering across the country. Highlights: National Progress: The national metering rate increased to 61.51% by the end of June, up from 60.22% in May. Meter Deployment: DisCos metered 203,521 additional customers in […]