Generation License Application

Generation License Application

The Nigerian Electricity Regulatory Commission (NERC) issues Generation Licenses to operators of electricity generation plants across three categories: On-grid, Off-grid, and Embedded generation. This license authorizes the holder to construct, own, operate, and maintain a power generation facility.

 

Licence Type Description Typical Capacity
On-grid Generation connected to the national transmission network All capacities
Off-grid Standalone generation not connected to the grid All capacities
Embedded Generation connected to the distribution network Typically smaller scale

Application Requirements

Mandatory Documents

All applicants must submit the following:

  1. Completed application form
  2. Certificate of incorporation and memorandum/articles of association (or deed of partnership/trust)
  3. Registered title deed to site, sale agreement, deed of assignment/gift, or evidence of submission to land processing agency
  4. Tax clearance certificate for the immediate past three (3) years
  5. Ten-year business plan
  6. Off-take agreement or arrangement (Power Purchase Agreement)
  7. Environmental Impact Assessment (EIA) approval certificate, or proof of submission to the Ministry of Environment, or effluent management plan (for plants <10MW)
  8. Fuel supply agreement or letter from fuel supplier/transporter confirming inclusion in supply plans
  9. MoU or letter of intent from EPC contractor (if applicable)
  10. MoU or letter of intent from technical partner (if applicable)
  11. Financing agreements or funding letter from financial institution(s)
  12. Timelines for commissioning and phased capacity rollout

 

Technical Documentation

Category Required Documents
Site Information • Site Map (fuel delivery, storage, transmission evacuation, pipelines, waste disposal)
• Location Map (roads, rail, transmission lines, rivers, reservoirs)
• Principal single-line diagram
Fuel & Water • Fuel sourcing, transportation and supply arrangements
• Water supply and availability analysis
Plant Design • Plant design specifications
• Power station information (capacity, units, size, annual generation, running regime, load factor)
• Generator unit technical specifications (type, rating, voltage, frequency, speed, efficiency, reactance, cooling, excitation, protection, governor control, transformer data, manufacturer details)
Contracts • EPC contract
• Phasing details (if applicable)
Ancillary Services • Black start facilities
• Reactive power generation capabilities
• Frequency response capability
• Maximum Generation (MAXGEN) capability
• Fast start capability
Grid Connection • Evacuation studies (load flow, stability, short circuit)
• TCN approval confirming connection point capacity
Safety & Environment • Emergency response plan
• Fire fighting facilities
• First Aid provisions
• Safety training plans
• Personal Protective Equipment (PPE)
• Health & Safety Policy
• Environmental Impact Assessment and waste management plan
Commissioning • Expected date of commissioning

 

 

 

Applicable Fees (Non-Refundable)

Applicable Fees (Non-Refundable)

On-Grid Generation

Processing Fees (paid on submission):

Capacity Fee (NGN)
1 – 10MW 75,000
11 – 50MW 150,000
51 – 100MW 200,000
101 – 200MW 250,000
201 – 300MW 350,000
301 – 400MW 400,000
401 – 500MW 450,000
Above 500MW 500,000

 

License Fees (paid after successful application, before granting):

Capacity Fee (USD)
1 – 10MW $5,000
11 – 50MW $30,000
51 – 100MW $40,000
101 – 200MW $60,000
201 – 300MW $80,000
301 – 400MW $100,000
401 – 500MW $120,000
Above 500MW $140,000

Off-Grid Generation

Processing Fees (paid on submission):

Capacity Fee (NGN)
1 – 10MW 50,000
11 – 25MW 150,000
26 – 40MW 175,000
41 – 60MW 225,000
61 – 85MW 250,000
86 – 100MW 275,000
101 – 200MW 300,000
201 – 400MW 400,000
401 – 500MW 500,000
Above 500MW 600,000

License Fees (paid after successful application, before granting):

Capacity Fee (USD)
1 – 10MW $10,000
11 – 25MW $35,000
26 – 40MW $40,000
41 – 60MW $45,000
61 – 85MW $50,000
86 – 100MW $55,000
101 – 200MW $75,000
201 – 400MW $95,000
401 – 500MW $150,000
Above 500MW $200,000

Note: Licence fees may be paid in US Dollars or Naira equivalent.

 

Processing Timeline

Standard Processing Time: 6 months from complete application submission

 

Embedded Generation Specific Requirements

In addition to mandatory documents, embedded generation applicants must provide draft agreements for:

  • Power Purchase Agreement
  • Connection Agreement
  • Use of Distribution System Agreement
  • Ancillary Services Agreement
  • Fuel Supply Agreement

And:

  • Environmental Impact Assessment approval (≥10MW) or effluent management policy (<10MW)
  • Registered title deed
  • Corporate documents (certificate of incorporation, memorandum/articles of association)

How to Apply

  1. Prepare all mandatory and technical documentation as listed above
  2. Pay the applicable processing fee based on your plant capacity
  3. Submit completed application form with all supporting documents to NERC
  4. Await application review and processing (6 months)
  5. Upon approval, pay the license fee
  6. Receive Generation License

Contact Information

Nigerian Electricity Regulatory Commission
Address: Plot 1387, Cadastral Zone A00, Central Business District, PMB 136, Garki, Abuja, FCT, Nigeria

Phone: +234-09-462-1400 / +234-09-462-1410

Email: info@nerc.gov.ng

Website: www.nerc.gov.ng]